Date Obligations & Warnings
Date obligations are basically date-based warnings to let you know when an activity happens too late (e.g., a spud needs to happen before a specific date per well).
Date obligations are really useful to handle lease stipulations around well timing, well expiry, etc. where you know activities must start or finish by a specific date.
To set up date obligations, there's a new "View Date Obligations" option under the Asset Templates actions:
|
You can describe which activities need to start (or finish) by any date attribute. In the example below, the date attribute is called "Required Spud Stip", but you can use any attribute you want.
|
If the activities happen too late, you'll get a warning about the obligation being missed:
|
As you can probably tell by the screenshots, date obligations are really easy to set up! They're an extremely useful way to catch timing problems live as you move wells around on your schedule.