How Asset Templates Work
- Asset templates: sets of activities and their relationships which drive the scheduling behavior. Assets must be assigned to a template to be included in a schedule
- Production start: determines when type well profile production will begin

- Relationships: defines dependencies between activities
- Duration: can be generic/flat inputs, calculations or look-ups to attributes for individual asset assumptions. Type an open bracket [ to expose attributes for calculated fields
- Delay: offsets between dependent activities

- Timing: determines whether activities should be scheduled as soon as possible, or as late as possible (i.e. just in time) without causing dependent activities to be delayed
- Grouping: ensures that assets with the same attribute are scheduled in sequence, using the same resource
- Resource: required resource type or named resources that must complete the activity